← Back to shortage queue

20-0070-06-FM

Tracker Post Kit, 6in Beam Rod, Top ACM Clamp, Tracking Build

Opening
0
Incoming
830
Outgoing
1,029
Ending balance
-199
First shortage
2026-04-17
Low point
-199
Low point date
2026-06-26
Type
Service

Projected Balance

-199-9902026-04-172026-04-272026-06-26DateProjected Balance

Top Recommendations

#1Pull in supplyClears shortage
Pull in supply to 2026-04-17 (10 days earlier)
Clears shortage; impacts 0 orders; changes qty 0.
Target date
2026-04-17
Source date
2026-04-27
Days shifted
-10
Orders impacted
0
Releases touched
0
Qty changed
0
Shortage cleared
Yes
Summary: Pull in PO to 2026-04-17 (10 days earlier).
Why ranked: Ranked 1 because it touches 0 release(s), moves qty 0, and changes timing by -10 day(s). Clears shortage with current simulated action set.

Event Table

DateTypeReferenceQty
2026-04-17Demand
Task 36938 (20-0070-06-FM)
Quote: Pelicans Jaw Flower West - CMS
35
2026-04-24Demand
Task 20569 (20-0070-06-FM)
Quote: Scenic Hill Warren SD Potlatch CMS
12
2026-04-24Demand
Task 20635 (20-0070-06-FM)
Quote: Scenic Hill Warren Co-located - CMS
16
2026-04-27Demand
Task 31297 (20-0070-06-FM)
Quote: Swenson Ranch - CMS and Bonsai
830
2026-04-27Supply
PO 3533
Supplier: FabMasters
830
2026-06-05Demand
Task 34559 (20-0070-06-FM)
Quote: Hilde - CMS
56
2026-06-26Demand
Task 24706 (20-0070-06-FM)
Quote: Anika - CMS
38
2026-06-26Demand
Task 24993 (20-0070-06-FM)
Quote: Novel Energy - Lindquist CMS
42