30-0097
Messenger Cable, ACM, 1/0
Opening
8,000
Incoming
4,378,000
Outgoing
4,448,500
Ending balance
-62,500
First shortage
2026-04-27
Low point
-62,500
Low point date
2026-06-26
Type
Inventory Item
Projected Balance
Top Recommendations
#1Pull in supplyClears shortage
Pull in supply to 2026-04-27 (7 days earlier)
Clears shortage; impacts 0 orders; changes qty 0.
Target date
2026-04-27
Source date
2026-05-04
Days shifted
-7
Orders impacted
0
Releases touched
0
Qty changed
0
Shortage cleared
Yes
Summary: Pull in PO to 2026-04-27 (7 days earlier).
Why ranked: Ranked 1 because it touches 0 release(s), moves qty 0, and changes timing by -7 day(s). Clears shortage with current simulated action set.
Event Table
| Date | Type | Reference | Qty |
|---|---|---|---|
| 2026-04-20 | Demand | Task 21544 Quote: Maple Leaf - CMS | 48,000 |
| 2026-04-20 | Demand | Task 33282 Quote: Sunflower Sky - CMS Rev#1 | 28,000 |
| 2026-04-20 | Supply | PO 3278 Supplier: Lonestar Electric Supply Industrial | 48,000 |
| 2026-04-20 | Supply | PO 3665 Supplier: Lonestar Electric Supply Industrial | 28,000 |
| 2026-04-22 | Demand | Task 32958 Quote: Winchester II - CMS | 70,000 |
| 2026-04-22 | Demand | Task 37854 Quote: Buffalo Spare Parts REV1 | 500 |
| 2026-04-22 | Supply | PO 3647 Supplier: Lonestar Electric Supply Industrial | 70,000 |
| 2026-04-23 | Demand | Task 35279 Quote: Abes Run - CMS | 11,000 |
| 2026-04-23 | Supply | PO 3816 Supplier: Lonestar Electric Supply Industrial | 11,000 |
| 2026-04-24 | Demand | Task 20569 Quote: Scenic Hill Warren SD Potlatch CMS | 1,000 |
| 2026-04-24 | Demand | Task 20635 Quote: Scenic Hill Warren Co-located - CMS | 2,000 |
| 2026-04-24 | Demand | Task 21262 Quote: Scenic Hill Solar - Fordyce - CMS REV1 | 1,000 |
| 2026-04-24 | Demand | Task 37661 Quote: Jones City 1 Spare Parts | 3,000 |
| 2026-04-27 | Demand | Task 31296 Quote: Swenson Ranch - CMS and Bonsai | 355,000 |
| 2026-04-27 | Demand | Task 32194 Quote: Hidden Meadows - CMS CO1 | 4,000 |
| 2026-04-27 | Demand | Task 32951 Quote: Libra - CMS | 427,000 |
| 2026-04-27 | Demand | Task 34349 Quote: POCOMOKE - CMS (WITH BONSAI) | 4,000 |
| 2026-04-27 | Demand | Task 34984 Quote: Milano - CMS CO1 | 185,000 |
| 2026-04-27 | Demand | Task 36056 Quote: Overnight Solar Project - CMS | 61,000 |
| 2026-04-27 | Demand | Task 36684 Quote: Cat Claw - O&M Spares | 1,000 |
| 2026-04-27 | Supply | PO 3532 Supplier: Lonestar Electric Supply Industrial | 355,000 |
| 2026-04-27 | Supply | PO 3641 Supplier: Lonestar Electric Supply Industrial | 427,000 |
| 2026-04-27 | Supply | PO 3789 Supplier: Lonestar Electric Supply Industrial | 185,000 |
| 2026-04-27 | Supply | PO 3875 Supplier: Lonestar Electric Supply Industrial | 61,000 |
| 2026-05-01 | Demand | Task 22231 Quote: Belfast Keene 3 - CMS | 1,000 |
| 2026-05-01 | Demand | Task 32168 Quote: Preston - CMS CO1 | 1,000 |
| 2026-05-01 | Demand | Task 37294 Quote: Hess - CMS | 3,000 |
| 2026-05-01 | Demand | Task 37307 Quote: Watkins - CMS | 2,000 |
| 2026-05-04 | Demand | Task 31661 Quote: Darden 3 - CMS with Bonsai CO1 | 214,000 |
| 2026-05-04 | Demand | Task 32150 Quote: Campbells - CMS CO2 | 14,000 |
| 2026-05-04 | Demand | Task 35139 Quote: Tehuacana - CMS | 283,000 |
| 2026-05-04 | Supply | PO 3553 Supplier: Lonestar Electric Supply Industrial | 214,000 |
| 2026-05-04 | Supply | PO 3592 Supplier: Lonestar Electric Supply Industrial | 14,000 |
| 2026-05-04 | Supply | PO 3808 Supplier: Lonestar Electric Supply Industrial | 283,000 |
| 2026-05-05 | Demand | Task 33699 Quote: Zeta Solar - CMS | 44,000 |
| 2026-05-05 | Supply | PO 3687 Supplier: Lonestar Electric Supply Industrial | 44,000 |
| 2026-05-08 | Demand | Task 35084 Quote: KN216 - CMS | 3,000 |
| 2026-05-11 | Demand | Task 36745 Quote: Imperial Sun - CMS | 27,000 |
| 2026-05-11 | Supply | PO 3944 Supplier: Lonestar Electric Supply Industrial | 27,000 |
| 2026-05-13 | Demand | Task 36757 Quote: Old Stage - CMS | 3,000 |
| 2026-05-18 | Demand | Task 31683 Quote: Darden 4 - CMS with Bonsai CO1 | 220,000 |
| 2026-05-18 | Demand | Task 36544 Quote: Pecan Prairie - North CMS | 153,000 |
| 2026-05-18 | Supply | PO 3559 Supplier: Lonestar Electric Supply Industrial | 220,000 |
| 2026-05-18 | Supply | PO 3932 Supplier: Lonestar Electric Supply Industrial | 153,000 |
| 2026-05-19 | Demand | Task 37467 Quote: Osmond - CMS | 2,000 |
| 2026-05-22 | Demand | Task 37734 Quote: EDF Crooked Creek - CMS | 4,000 |
| 2026-05-22 | Demand | Task 37751 Quote: Ursa Creek - CMS | 3,000 |
| 2026-05-22 | Demand | Task 37770 Quote: Rainbow Lake - CMS | 2,000 |
| 2026-05-25 | Demand | Task 34151 Quote: Frontier 2 - CMS CO1 | 30,000 |
| 2026-05-25 | Demand | Task 35613 Quote: Blacks Creek - CMS- Base Quote | 221,000 |
| 2026-05-25 | Demand | Task 36409 Quote: Adams Creek - CMS | 6,000 |
| 2026-05-25 | Demand | Task 36562 Quote: Meadowbrook - CMS | 4,000 |
| 2026-05-25 | Demand | Task 36577 Quote: Vetter - CMS | 2,000 |
| 2026-05-25 | Demand | Task 36594 Quote: Buscho - CMS | 3,000 |
| 2026-05-25 | Demand | Task 36606 Quote: Cedar Creek - Landfill CMS | 3,000 |
| 2026-05-25 | Demand | Task 36619 Quote: Fitzthum 2 CMS | 1,000 |
| 2026-05-25 | Supply | PO 3722 Supplier: Lonestar Electric Supply Industrial | 30,000 |
| 2026-05-25 | Supply | PO 3834 Supplier: Lonestar Electric Supply Industrial | 221,000 |
| 2026-05-25 | Supply | PO 3916 Supplier: Lonestar Electric Supply Industrial | 6,000 |
| 2026-05-27 | Demand | Task 36087 Quote: Comfort Street - CMS | 3,000 |
| 2026-05-29 | Demand | Task 36015 Quote: Eagle Creek - CMS | 104,000 |
| 2026-05-29 | Supply | PO 3873 Supplier: Lonestar Electric Supply Industrial | 104,000 |
| 2026-06-01 | Demand | Task 16896 Quote: Squab Solar CMS | 64,000 |
| 2026-06-01 | Demand | Task 34152 Quote: Frontier 2 - CMS CO1 | 30,000 |
| 2026-06-01 | Demand | Task 36895 Quote: Milano - CMS CO1 | 2,000 |
| 2026-06-01 | Supply | PO 2976 Supplier: Lonestar Electric Supply Industrial | 64,000 |
| 2026-06-01 | Supply | PO 3722 Supplier: Lonestar Electric Supply Industrial | 30,000 |
| 2026-06-02 | Demand | Task 35651 Quote: Star Dairy - CMS | 71,000 |
| 2026-06-02 | Supply | PO 3840 Supplier: Lonestar Electric Supply Industrial | 71,000 |
| 2026-06-05 | Demand | Task 24747 Quote: Chisme - CMS/SUMAC/BESS Route B_Rev1 | 69,000 |
| 2026-06-05 | Demand | Task 34559 Quote: Hilde - CMS | 1,000 |
| 2026-06-05 | Demand | Task 35022 Quote: Lucy Solar CMS | 217,000 |
| 2026-06-05 | Demand | Task 35088 Quote: KN335- CMS | 3,000 |
| 2026-06-05 | Supply | PO 3490 Supplier: Lonestar Electric Supply Industrial | 69,000 |
| 2026-06-05 | Supply | PO 3794 Supplier: Lonestar Electric Supply Industrial | 217,000 |
| 2026-06-08 | Demand | Task 34153 Quote: Frontier 2 - CMS CO1 | 31,000 |
| 2026-06-08 | Supply | PO 3722 Supplier: Lonestar Electric Supply Industrial | 31,000 |
| 2026-06-11 | Demand | Task 35913 Quote: Tierra Blanco - CMS 4ft Spacing | 181,000 |
| 2026-06-11 | Supply | PO 3862 Supplier: Lonestar Electric Supply Industrial | 181,000 |
| 2026-06-12 | Demand | Task 36144 Quote: Grant Solar - CMS and SUMAC | 72,000 |
| 2026-06-12 | Supply | PO 3881 Supplier: Lonestar Electric Supply Industrial | 72,000 |
| 2026-06-15 | Demand | Task 36412 Quote: Adams Creek - CMS | 150,000 |
| 2026-06-15 | Demand | Task 36855 Quote: Mt. Olive Creek - CMS | 49,000 |
| 2026-06-15 | Supply | PO 3916 Supplier: Lonestar Electric Supply Industrial | 150,000 |
| 2026-06-15 | Supply | PO 3952 Supplier: Lonestar Electric Supply Industrial | 49,000 |
| 2026-06-26 | Demand | Task 22760 Quote: Novel Energy - Swartley CMS | 2,000 |
| 2026-06-26 | Demand | Task 23799 Quote: Darell - CMS CO1 | 1,000 |
| 2026-06-26 | Demand | Task 23886 Quote: Ellingson - CMS | 1,000 |
| 2026-06-26 | Demand | Task 24706 Quote: Anika - CMS | 1,000 |
| 2026-06-26 | Demand | Task 24993 Quote: Novel Energy - Lindquist CMS | 1,000 |
| 2026-06-26 | Demand | Task 31499 Quote: Scotts Hill - CMS | 1,000 |
| 2026-06-26 | Demand | Task 34058 Quote: Solar Club 31 - CMS | 1,000 |
| 2026-07-03 | Demand | Task 37110 Quote: Great Plains - CMS | 39,000 |
| 2026-07-03 | Demand | Task 37199 Quote: Switchgrass - CMS | 48,000 |
| 2026-07-03 | Demand | Task 37876 Quote: Lupinus II - CMS | 103,000 |
| 2026-07-03 | Supply | PO 3978 Supplier: Lonestar Electric Supply Industrial | 39,000 |
| 2026-07-03 | Supply | PO 3985 Supplier: Lonestar Electric Supply Industrial | 48,000 |
| 2026-07-03 | Supply | PO 4052 Supplier: Lonestar Electric Supply Industrial | 103,000 |
| 2026-07-13 | Demand | Task 37371 Quote: Woodridge - CMS | 60,000 |
| 2026-07-13 | Supply | PO 3999 Supplier: Lonestar Electric Supply Industrial | 60,000 |
| 2026-09-04 | Demand | Task 35991 Quote: Henderson - CMS | 46,000 |
| 2026-09-04 | Supply | PO 3870 Supplier: Lonestar Electric Supply Industrial | 46,000 |
| 2026-10-19 | Demand | Task 34444 Quote: Zydeco Solar - CMS | 80,000 |
| 2026-10-19 | Supply | PO 3739 Supplier: Lonestar Electric Supply Industrial | 80,000 |
| 2026-10-21 | Demand | Task 37506 Quote: Waller Solar - CMS | 98,000 |
| 2026-10-21 | Supply | PO 4010 Supplier: Lonestar Electric Supply Industrial | 98,000 |
| 2026-11-30 | Demand | Task 31666 Quote: Darden 1 - CMS with Bonsai CO1 | 232,000 |
| 2026-11-30 | Supply | PO 3556 Supplier: Lonestar Electric Supply Industrial | 232,000 |
| 2026-12-28 | Demand | Task 31702 Quote: Darden 2 - CMS with Bonsai CO1 | 237,000 |
| 2026-12-28 | Supply | PO 3562 Supplier: Lonestar Electric Supply Industrial | 237,000 |