30-0459-01
Bracket, GCS Reinforcement, 4.5in
Opening
37
Incoming
363
Outgoing
400
Ending balance
0
First shortage
2026-04-27
Low point
-10
Low point date
2026-04-27
Type
Inventory Item
Projected Balance
Top Recommendations
#1Pull in supplyClears shortage
Pull in supply to 2026-04-27 (14 days earlier)
Clears shortage; impacts 0 orders; changes qty 0.
Target date
2026-04-27
Source date
2026-05-11
Days shifted
-14
Orders impacted
0
Releases touched
0
Qty changed
0
Shortage cleared
Yes
Summary: Pull in PO to 2026-04-27 (14 days earlier).
Why ranked: Ranked 1 because it touches 0 release(s), moves qty 0, and changes timing by -14 day(s). Clears shortage with current simulated action set.
#2Split releaseClears shortage
Split release to 2026-05-11 (14 days later)
Clears shortage; impacts 1 order; changes qty 10.
Target date
2026-05-11
Source date
2026-04-27
Days shifted
14
Orders impacted
1
Releases touched
1
Qty changed
10
Shortage cleared
Yes
Summary: Split release 32196 to 2026-05-11 (14 days later) and move only qty 10.
Why ranked: Ranked 2 because it touches 1 release(s), moves qty 10, and changes timing by 14 day(s). Clears shortage with current simulated action set.
#3Split releaseClears shortage
Split release to 2026-05-11 (14 days later)
Clears shortage; impacts 1 order; changes qty 10.
Target date
2026-05-11
Source date
2026-04-27
Days shifted
14
Orders impacted
1
Releases touched
1
Qty changed
10
Shortage cleared
Yes
Summary: Split release 34349 to 2026-05-11 (14 days later) and move only qty 10.
Why ranked: Ranked 3 because it touches 1 release(s), moves qty 10, and changes timing by 14 day(s). Clears shortage with current simulated action set.
Event Table
| Date | Type | Reference | Qty |
|---|---|---|---|
| 2026-03-20 | Supply | PO 3801 Supplier: General Stamping & Metalworks | 98 |
| 2026-04-27 | Demand | Task 32196 Quote: Hidden Meadows - CMS CO1 | 157 |
| 2026-04-27 | Demand | Task 34349 Quote: POCOMOKE - CMS (WITH BONSAI) | 145 |
| 2026-04-27 | Supply | PO 3806 Supplier: General Stamping & Metalworks | 157 |
| 2026-05-11 | Supply | PO 3793 Supplier: General Stamping & Metalworks | 108 |
| 2026-06-05 | Demand | Task 35090 Quote: KN335- CMS | 98 |