← Back to shortage queue

31-0255-01

CMS Hanger, .398in Messenger, 4-Seat x 2-Cable

Opening
2,464
Incoming
73,472
Outgoing
57,460
Ending balance
18,476
First shortage
2026-05-13
Low point
-12,660
Low point date
2026-05-13
Type
Inventory Item

Projected Balance

-12,66023,62859,9162026-05-012026-05-192026-06-18DateProjected Balance

Top Recommendations

#1Pull in supplyClears shortage
Pull in supply to 2026-05-13 (5 days earlier)
Clears shortage; impacts 0 orders; changes qty 0.
Target date
2026-05-13
Source date
2026-05-18
Days shifted
-5
Orders impacted
0
Releases touched
0
Qty changed
0
Shortage cleared
Yes
Summary: Pull in PO to 2026-05-13 (5 days earlier).
Why ranked: Ranked 1 because it touches 0 release(s), moves qty 0, and changes timing by -5 day(s). Clears shortage with current simulated action set.
#2Split releaseClears shortage
Split release to 2026-05-18 (5 days later)
Clears shortage; impacts 1 order; changes qty 12,660.
Target date
2026-05-18
Source date
2026-05-13
Days shifted
5
Orders impacted
1
Releases touched
1
Qty changed
12,660
Shortage cleared
Yes
Summary: Split release 35455 to 2026-05-18 (5 days later) and move only qty 12660.
Why ranked: Ranked 2 because it touches 1 release(s), moves qty 12660, and changes timing by 5 day(s). Clears shortage with current simulated action set.
#3Move minimal release setClears shortage
Move minimal release set to 2026-05-18 (5 days later)
Clears shortage; impacts 1 order; changes qty 13,892.
Target date
2026-05-18
Source date
2026-05-13
Days shifted
5
Orders impacted
1
Releases touched
1
Qty changed
13,892
Shortage cleared
Yes
Summary: Move the minimal post-shortage release set to 2026-05-18 (5 days later).
Why ranked: Ranked 3 because it touches 1 release(s), moves qty 13892, and changes timing by 5 day(s). Clears shortage with current simulated action set.

Event Table

DateTypeReferenceQty
2026-05-01Demand
Task 37294
Quote: Hess - CMS
1,120
2026-05-08Demand
Task 35086
Quote: KN216 - CMS
112
2026-05-13Demand
Task 35455
Quote: Hoke CMS CO2
13,892
2026-05-18Supply
PO 3676
Supplier: SPG Global
25,088
2026-05-19Demand
Task 37467
Quote: Osmond - CMS
896
2026-06-01Supply
PO 3788
Supplier: Zetwerk
7,168
2026-06-10Supply
PO 3888
Supplier: SPG Global
17,920
2026-06-10Supply
PO 3888
Supplier: SPG Global
10,752
2026-06-17Supply
PO 3888
Supplier: SPG Global
12,544
2026-06-18Demand
Task 35914
Quote: Tierra Blanco - CMS 4ft Spacing
41,440