← Back to shortage queue

32-0204-04

Module Cable Hanger, Straight Hook, 8X #8awg

Opening
0
Incoming
1,448,400
Outgoing
1,448,400
Ending balance
0
First shortage
2026-05-04
Low point
-17,000
Low point date
2026-05-04
Type
Inventory Item

Projected Balance

-17,000-8,50002026-04-272026-05-112026-06-15DateProjected Balance

Top Recommendations

#1Pull in supplyClears shortage
Pull in supply to 2026-05-04 (7 days earlier)
Clears shortage; impacts 0 orders; changes qty 0.
Target date
2026-05-04
Source date
2026-05-11
Days shifted
-7
Orders impacted
0
Releases touched
0
Qty changed
0
Shortage cleared
Yes
Summary: Pull in PO to 2026-05-04 (7 days earlier).
Why ranked: Ranked 1 because it touches 0 release(s), moves qty 0, and changes timing by -7 day(s). Clears shortage with current simulated action set.
#2Move minimal release setClears shortage
Move minimal release set to 2026-05-11 (7 days later)
Clears shortage; impacts 1 order; changes qty 17,000.
Target date
2026-05-11
Source date
2026-05-04
Days shifted
7
Orders impacted
1
Releases touched
1
Qty changed
17,000
Shortage cleared
Yes
Summary: Move the minimal post-shortage release set to 2026-05-11 (7 days later).
Why ranked: Ranked 2 because it touches 1 release(s), moves qty 17000, and changes timing by 7 day(s). Clears shortage with current simulated action set.
#3Move releaseClears shortage
Move release to 2026-05-11 (7 days later)
Clears shortage; impacts 1 order; changes qty 17,000.
Target date
2026-05-11
Source date
2026-05-04
Days shifted
7
Orders impacted
1
Releases touched
1
Qty changed
17,000
Shortage cleared
Yes
Summary: Move release 33316 to 2026-05-11 (7 days later) to reduce near-term shortage exposure.
Why ranked: Ranked 3 because it touches 1 release(s), moves qty 17000, and changes timing by 7 day(s). Clears shortage with current simulated action set.

Event Table

DateTypeReferenceQty
2026-04-27Demand
Task 32198
Quote: Hidden Meadows - CMS CO1
1,700
2026-04-27Supply
PO 3596
Supplier: Master Spring & Wire Form Co., Inc
1,700
2026-05-04Demand
Task 33316
Quote: Campbells - CMS CO2
17,000
2026-05-11Supply
PO 3668
Supplier: Master Spring & Wire Form Co., Inc
17,000
2026-05-18Demand
Task 37581
Quote: Mayes Solar - CMS CO1
224,400
2026-05-18Supply
PO 4018
Supplier: Master Spring & Wire Form Co., Inc
224,400
2026-05-25Demand
Task 36418
Quote: Adams Creek - CMS
5,300
2026-05-25Supply
PO 3919
Supplier: Master Spring & Wire Form Co., Inc
5,300
2026-06-15Demand
Task 36419
Quote: Adams Creek - CMS
1,200,000
2026-06-15Supply
PO 3919
Supplier: Master Spring & Wire Form Co., Inc
1,200,000